Goal:
Support the ability to associate/link change requests to change sets instead of directly to resources.
Prerequisites:
- AM repository with history enabled (change tracking)
- AM system with a connection to a CM system
- Multiple change requests created in the CM system that will require modification of the same resource(s) in the AM repository
- Each change request assigned to a user, could be the same user or different users, the scenario uses different users
Outcomes:
- Change request 1 linked to a change set in the AM repository
- Change request 2 linked to a change set in the AM repository
- Given a change request find the change set(s) and all Resource(s) affected in the AM repository
- Given a resource find all change request(s) that affect the resource in the AM repository
Scenario
- User1 establishes a context in the AM tool
- User 1 opens existing AM repository - Proj1/Wksp1
- User 1 selects an existing change request - CR1 from a list of assigned requests retrieved from the CM system
- All changes made will now be tracked and related to the active change request CR1
- User1 assesses the scope of the change request
- Locate AM resource(s) Res1 impacted by the request - CR1
- User1 Applies required changes
- Open AM resource - Res1 and make required changes (Res1 is locked while being modified)
- Save AM resource - Res1
- Change set created and association with the active change request - CR1 is established
- Resource Res1 is unlocked
- User2 establishes a context in the AM tool
- User 2 opens existing AM repository - Proj1/Wksp1
- User 2 selects an existing change request - CR2 from a list of assigned requests retrieved from the CM system
- All changes made will now be tracked and related to the active change request CR2
- User2 Assesses scope of Change Request
- Locate AM resource(s) impacted by the request- Res1
- User2 Applies required changes
- Open AM resource - Res1 and make required changes (Res1 is locked while being modified)
- Save AM resource - Res1
- Change set created and association with the active change request - CR2 is established
- Resource Res1 is unlocked
- User3 reviews the changes for each change request
- Opens existing AM repository - Proj1/Wksp1
- Selects CR1 and is able to view a list of the changes made to Res1 on behalf of CR1
- Selects CR2 and is able to view a list of the changes made to Res1 on behalf of CR2
Goal:
In architecture artifacts (object x) an architect (role) would create a link from a high-level design object (object y), such as a data controller component, to a high-level testing artifact (object z), such as a test plan.